Earthwork Services for RDA
Stage 15, 16, 17 and 18. The Newmont Boddington Gold (NBG) operation was built on an existing mine lease and is now one of Australia’s largest gold mines.

Charles Hull Contracting

Stage 15, 16, 17 and 18. The Newmont Boddington Gold (NBG) operation was built on an existing mine lease and is now one of Australia’s largest gold mines.

Raising wall of tailings storage facility with installation of underdrainage. Effective trimming using GPS, Reduction in survey costs, Positive communication with client on progress, Project finished on time and on budget

The project involved the construction of 1200km of haul roads for a long term client.

The project involved the construction of a new crusher circle and facilities area.

Construct a 1.2 km extension to current runway while planes still operated from the old runway which was then upgraded once the new extension was completed. The planes then switched to operating from the new extension whilst upgrade was carried out on old runway.

The project involved the rehabilitation of mining pits and haul roads. 1430 ha of rehabilitation completed, 13 major creek crossings removed, 950 ha of DRT soil spreading, 144 ha of conventional DRT

This project was first season in rehabilitation of a mineral sand mine site. The scope of work involved removing all waste material, backfilling mining area, replacing organic sand and topsoil ready for planting of native vegetation and pasture.

This project built a 44 hectare residue storage area and a 23 hectare runoff collection pond. Charles Hull Contracting (CHC) were engaged to complete this project by Alcoa of Australia at their residue storage area located in Wagerup, WA.

Construction of a bulk grain storage facility in the Wheatbelt region. Charles Hull Contracting (CHC) were engaged to complete this project by Bunge Australia at their bulk storage site located in Kukerin, WA.

The project involved the staged construction of a Residue Disposal Area over 2 years. A large part of the project involved the construction of the upstream embankment using tailings material and clay.

Charles Hull Contracting (CHC) were engaged to complete this project by Water Corporation and the Shire of Waroona at the Coronation Rd bridge located 7.5km west of Waroona, WA.

The project involved the construction of 4 Grain Pads and the access road. The initial contract was to build 1 grain bulkhead, this turned into constructing 4 bulkheads.