Client:
ALCOA
Project:
Huntly Myara Civils Project
Location:
Huntly Minesite, WA
Summary:
The project involved the construction of a new crusher circle and facilities area.
- A sound knowledge of civil activities with a huge reduction in costs.
- Strong resource management.
- Constructive scheduling and planning to meet important milestones.
- Maintained positive relationship with client to complete works.
Key activities:
- Haul road construction,
- 190 ML water dam constructed,
- Conveyor trace earthworks,
- Tunnel works,
- Stormwater drainage,
- Sewer drainage,
- Culvert installation,
- Liner installation,
- Bitumen two coat seal,
- Asphalt placement.