TSF Wall Lift

Raising wall of tailings storage facility with installation of underdrainage. Effective trimming using GPS, Reduction in survey costs, Positive communication with client on progress, Project finished on time and on budget

Haul Road Construction

Client: ALCOA Project: Haul Road Construction Location: Huntly and Willowdale, WA Summary: The project involved the construction of 1200km of haul roads for a long term client. CHC maintained a good understanding of the job scope. Strong resource management to maintain targets set by the client. A good working relationship was held between CHC and […]

Huntly Myara Civils Project

Client: ALCOA Project: Huntly Myara Civils Project Location: Huntly Minesite, WA Summary: The project involved the construction of a new crusher circle and facilities area. A sound knowledge of civil activities with a huge reduction in costs. Strong resource management. Constructive scheduling and planning to meet important milestones. Maintained positive relationship with client to complete […]

McArthur River Airstrip

Client: Xstrata Project: McArthur River Airstrip Location: McArthur River Mine, NT Summary: Construct extension to airstrip and upgrade old runway. To construct a 1.2 km extension to current runway while planes still operated from the old runway which was then upgraded once the new extension was completed. The planes then switched to operating from the […]

McCoy Rehabilitation

The project involved the rehabilitation of mining pits and haul roads. 1430 ha of rehabilitation completed, 13 major creek crossings removed, 950 ha of DRT soil spreading, 144 ha of conventional DRT

Gwindinup Sand Mine

This project was first season in rehabilitation of a mineral sand mine site. The scope of work involved removing all waste material, backfilling mining area, replacing organic sand and topsoil ready for planting of native vegetation and pasture.

RSA9 and ROCP3 Project

This project built a 44 hectare residue storage area and a 23 hectare runoff collection pond. Charles Hull Contracting (CHC) were engaged to complete this project by Alcoa of Australia at their residue storage area located in Wagerup, WA.

Kukerin Grain Storage Facility

Construction of a bulk grain storage facility in the Wheatbelt region. Charles Hull Contracting (CHC) were engaged to complete this project by Bunge Australia at their bulk storage site located in Kukerin, WA.

NBG Residue Disposal Area

The project involved the staged construction of a Residue Disposal Area over 2 years. A large part of the project involved the construction of the upstream embankment using tailings material and clay.

Coronation Road Bridge

Charles Hull Contracting (CHC) were engaged to complete this project by Water Corporation and the Shire of Waroona at the Coronation Rd bridge located 7.5km west of Waroona, WA.